Tender cost
[edit] introduction
Usually created as a response to an invitation to tender (ITT), a tender is a submission made by a prospective supplier (the tenderer) which makes an offer for the supply of goods or services. In construction terms the tender could be for the construction of an entire building or buildings, or for providing a distinct set of services such as landscaping.
A tender pricing document sets out the way in which the cleint wishes to review the breakdown of the overall tender prices provided by tendering suppliers. It is effectively an unpriced bill of quantities. The completed tender pricing document is effectively a priced bill of quantities; it sets out the tenderer’s rates, costs and totals and constitutes the tenderer’s complete offer to the client.
The tender cost is the total of all the charges contained in the tender that will be made by the supplier associated with the delivery of the tender requirements. To the client (who issued the ITT), the tender cost usually represents the total cost of taking delivery of the building or service.
Costs in the tender will be broken down and itemised against each stated requirement. This not only makes it easier for tenderers to price the document, it also means clients and their advisers can see exactly what is being offered by the various tenderers, make comparisons between them, see where value lies and where savings can be made.
[edit] Two-stage tendering
Two-stage tendering is used to allow early appointment of a supplier, prior to the completion of all the information required to enable them to offer a fixed price. In the first stage, a limited appointment is agreed allowing the supplier to begin work and in the second stage a fixed price is negotiated for the contract. It can be used to appoint the main contractor early or more commonly as a mechanism for early appointment of a specialist supplier such as a cladding contractor.
[edit] Related articles on Designing Buildings Wiki
- Accounting.
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Business plan.
- Cash flow.
- Common arrangement of work sections.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Initial cost appraisals.
- New Rules of Measurement.
- Pre-tender estimate.
- Spon's Price Book.
- Tender documentation.
- Tender pricing document
- Types of bill of quantities.
- Whole-life costs.
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.